The project parties involved in the Core Flow-Based Market Coupling project (Core FB MC) inform that Full Integration Testing (FIT), focused on functionality between all systems involved in the FB MC process, finished successfully on 13th January 2022. The next phase of the testing – Simulation Integration Testing (SIT) has started on 17th January 2022 and is expected to run until the end of February 2022. The SIT testing is focused on testing of the joint operational procedures to prove, that the solution is capable of facilitating the daily operational process.
The new go-live date of Core FB MC will be 20th April 2022, trading day for delivery on 21st April 2022.
The full press release is available HERE.
Share