Updated planning of the DE-AT-PL-4M MC (Interim Coupling) Project

Share

The project parties of the DE-AT-PL-4M MC (Interim Coupling) Project hereby inform stakeholders about the slight update of the project planning. The Member Tests with the participation of market participants is now envisaged to be carried out between 31st May 2021 and 7th June 2021. The go-live of the project is being postponed from 10th June to 17th June 2021.
 
More details can be found in the press release available HERE.